Project Description
Scope of Work
The scope of work of this EPC Project includes Engineering, Supply, Installation and Testing & Commissioning of two132/13.8 KV Substations as follows:
- 3 Bays 132 GIS Ext.
- 30 Breakers 13.8 KV
- 33 KV Switchgears
- 3 X 40 + 2 X 40 MVA Transformers
- Protection & Control System
- SCADA System
- Sequences of Event Recorders
- Transient Fault Recorders
- Electromechanical Work
- HVAC Work
- Civil Work / Buildings :
- GIS / Switchgear Building} 1,000 m2
- Medium Voltage/Control Building}