Print
Project Details
Location
Value in SR
Client
Period
Type
Consultant

Project Description

Scope of Work
The Najran Central Power Station shall be extended by 1 x 50 MW (Main) supplied by General Electric and 1 x 50 MW (Optional), out door packaged Gas Turbine

Generator sets utilizing crude / diesel fuel oil. The pertaining mechanical systems of this extension shall be provided to allow safe and reliable operation of the new gas turbines (1 x 50 MW Main and 1 x 50 MW Optional G/T Generator sets)

Najran, Saudi Arabia
137 Millions
SCECO-South
Dec. 1995 To Nov. 1998
POWER GENERATION & TRANSMISSION
By the Client