| Dated: 04-05-2010 |
|
First Fire - Qurayyah Power Plant Phase B
|
|
Fourteen (14) Units Synchronized successfully for Qurayyah Power Plant Phase B as of Mar 28, 2010 and First Fire for the last Unit (Unit # 15) on May 4, 2010.
Please visit our Projects Section under " Construction of Qurayyah Open Cycle Power Plant" for more project information. |
|
|
|
| |
|
|