Major Projects

Riyadh Power Plant No.9 Combined Cycle (5,980 MW)

The combined cycle plant (PP9) has been built on a site of 3.2 million square meter about 54km east of Riyadh. This construction, together with an expansion of the existing PP 9 facility, made Riyadh the largest crude oil-fired power plant in the world. Arabian Bemco Contracting Company was awarded the project by SEC. Works Started in 1995,

Riyadh Power Plant No.10 Combined Cyle (4,600 MW)

On June 30, 2008 Arabian Bemco was awarded a S.R 11 billion (USD 3 billion) contract with SEC for a turnkey supply and installationof a 2,600 MW power geneartion plant (PP10) built on an area of 5 million square meter outside the capital of Saudi Arabia, Riyadh.This is a Greenfield project that will initially install 36 GTG simple cycle base loaded gas turbines on

Qurayyah Combined Cycle Project (4,600 MW)

On June 11, 2007, Arabian Bemco was awarded a SR 2.1 billion (USD 570 Million) contract with SEC to build the 2,500 MW Qurrayah Open Cycle Power Plant in the Eastern Province of KSA. Under the engineering, civil construction and mechanical erection package, Arabian Bemco will install gas-fired turbines at the plant supplied by

Riyadh Power Plant No.12 Combined Cycle (2,175 MW)

On May 16, 2012, Arabian Bemco signed a S.R 4.7 billion contract (USD 1.3 billion) with the Saudi Electricity Company to build a Grass Root Combined Cycle Power Plant in Riyadh, Saudi Arabia. The plant is located 100 KM West of Riyadh City. Once completed, the new grass root combined cycle power plant (PP12) will produce


Project Details
Location
Value in SR
Client
Period
Type
Consultant

Project Description
The project scope is a turn key job including detailed engineering, supply, installation, testing, commissioning and one year warranty of chiller plant to produce 30,000 tons of refrigeration.

Scope of Work

  • Ten (10) chiller units with 2,500 tons nominal each.
  • Thermal energy storage (TES) tank providing the remainder of the capacity.
  • Eight (8) cells cooling towers.
  • Chilled water pumps and condenser water pumps.
  • Instrumentation and controls.
  • Electric power supply.
  • Equipment variable frequency drives.
  • Building construction with approximate dimension of 61 meters by 56 meters inclusive of basement, ground floor, mezzanine floor and roof.
  • Building services including air conditioning, plumbing, electrical and fire fighting works.
  • Site developing, roads, walkways, Employees Parking Spaces with canopy, Security Fence and gates etc.
  • TES Chilled Water Storage Tank, Water Storage Tanks.
Doha, Qatar
138 Millions
Qatar Cool
Feb 20, 2006 to Jul 20, 2007
COMPLETED INDUSTRIAL
Parsons International Ltd.

Relief System & Flare Gas System Qatif - Progress 2020

   Relief System & Flare Gas System Qatif - Progress 2020

Watch Video...